arete were engaged by Aveo Group to fitout their new head office in the Gasworks precinct.

The fitout included installation of multiple solid and glazed partitions to create separate areas for office and meetings uses, services upgrades, tiled lift lobby walls and floors, kitchens and a reception with high quality joinery and the installation of 120 workstations working through from the back of the office through to the other end.

arete worked closely with Ultralinea Architects to value engineer this project to reduce the costs to adhere with the client’s tight budget whilst still maintaining the design intent. This project was on a tight 5 week programme as Aveo had a mandatory move-in date.

There were challenges with logistics as the building was under construction and the level we were working on had no lift access however, arete still managed to deliver this 3,000m² gorgeous office space on time and on budget!